N-queens and solution pool

In [1], I described some chess-related problems. Here, I want to reproduce the \(n\)-queens problem. The single solution problem, placing as many queens on the chess board as possible so they don't attack each other, is pretty standard. I want to focus on the more complex question: How many different ways can we place those queens? In other words: what are all the optimal solutions? We can do this by adding a no-good constraint that forbids the previously found solution. However, as this problem has more than a handful of different solutions, I want to use the Cplex solution pool.

Single Solution Model

We define the decision variables as: \[\color{darkred}x_{i,j} = \begin{cases} 1 & \text{if we place a queen on the square $(i,j)$} \\ 0 & \text{otherwise}\end{cases}\] 

Chess Board


Wednesday, April 26, 2023

A large MIP model that should be solved as LP: the root node

In this post, I want to discuss an observation about the root node when solving a MIP model.

Problem Description


The model I want to tackle here is from [1]:

We have a large matrix \(\color{darkblue}A=\color{darkblue}a_{i,j}\) with values 0 and 1. In addition, we have a minimum on the row and column totals. These are called \(\color{darkblue}r_i\) and \(\color{darkblue}c_j\). The goal is to remove as many 1's in the matrix \(\color{darkblue}A\) subject to these minimum row and column totals.

Sunday, October 13, 2019

Sometimes a commercial solver is really better...

Solving a model with an integer valued objective, with 500 binary variables, gave some interesting results.

  • Cplex. Optimal solution \(z=60\) found in about 8 seconds. Using 4 threads on an old laptop. Log is below.
  • CBC. Hit timelimit of 2 hours. Objective = 62 (non-optimal). Also using 4 threads on the same machine. The strange thing is that with CBC the best possible bound is not changing at all. Not by a millimeter. See the highlighted numbers in the log below. CBC is a very good solver, but sometimes I see things like this.
  • Gurobi and Xpress solve this problem very fast. Ran on NEOS via an MPS file. 
  • SCIP has also problems with this model. Ran on NEOS via an MPS file.

All runs were with default settings. It looks like the commercial solvers do a much better job than the open source and academic codes. Sometimes you get what you pay for.

Cplex Log



Tried aggregator 2 times.
MIP Presolve eliminated 4 rows and 5 columns.
MIP Presolve modified 3 coefficients.
Aggregator did 500 substitutions.
Reduced MIP has 999 rows, 1499 columns, and 2497 nonzeros.
Reduced MIP has 500 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.02 sec. (7.38 ticks)
Found incumbent of value 500.000000 after 0.03 sec. (8.85 ticks)
Probing time = 0.00 sec. (0.20 ticks)
Tried aggregator 1 time.
Reduced MIP has 999 rows, 1499 columns, and 2497 nonzeros.
Reduced MIP has 500 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.00 sec. (5.26 ticks)
Probing time = 0.00 sec. (0.19 ticks)
MIP emphasis: balance optimality and feasibility.
MIP search method: dynamic search.
Parallel mode: deterministic, using up to 4 threads.
Parallel mode: deterministic, using up to 3 threads for concurrent optimization.
Tried aggregator 1 time.
LP Presolve eliminated 999 rows and 1499 columns.
All rows and columns eliminated.
Presolve time = 0.02 sec. (0.71 ticks)
Initializing dual steep norms . . .
Root relaxation solution time = 0.02 sec. (1.15 ticks)

        Nodes                                         Cuts/
   Node  Left     Objective  IInf  Best Integer    Best Bound    ItCnt     Gap

*     0+    0                          500.0000        0.0000           100.00%
Found incumbent of value 500.000000 after 0.06 sec. (16.78 ticks)
      0     0       55.2664   490      500.0000       55.2664        0   88.95%
*     0+    0                           75.0000       55.2664            26.31%
Found incumbent of value 75.000000 after 0.08 sec. (21.35 ticks)
      0     0       55.2825   353       75.0000     Cuts: 349      222   26.29%
      0     0       55.4160   311       75.0000     Cuts: 349      455   26.11%
      0     0       55.4160   275       75.0000     Cuts: 349      775   26.11%
*     0+    0                           72.0000       55.4160            23.03%
Found incumbent of value 72.000000 after 0.59 sec. (116.10 ticks)
      0     0       55.4160   182       72.0000     Cuts: 349     1032   23.03%
      0     0       55.4160   141       72.0000     Cuts: 349     1208   23.03%
      0     0       55.4160   121       72.0000     Cuts: 192     1336   23.03%
      0     0       55.4160   105       72.0000     Cuts: 128     1410   23.03%
      0     0       55.4160    98       72.0000      Cuts: 85     1472   23.03%
      0     0       55.4160    61       72.0000      Cuts: 74     1494   23.03%
      0     0       55.4160    67       72.0000     Cuts: 160     1571   23.03%
      0     2       55.4160    56       72.0000       55.4160     1571   23.03%
Elapsed time = 1.33 sec. (273.54 ticks, tree = 0.01 MB, solutions = 3)
   1239   854       55.4160    59       72.0000       55.4160     3845   23.03%
                                                     Cuts: 38                  
*  1471+ 1230                           71.0000       55.4160            21.95%
                                                     Cuts: 16                  
Found incumbent of value 71.000000 after 3.39 sec. (827.52 ticks)
*  1474+ 1230                           70.0000       55.4160            20.83%
Found incumbent of value 70.000000 after 3.39 sec. (828.63 ticks)
*  1481+ 1230                           69.0000       55.4160            19.69%
Found incumbent of value 69.000000 after 3.41 sec. (831.79 ticks)
*  1490+ 1230                           68.0000       55.4160            18.51%
Found incumbent of value 68.000000 after 3.44 sec. (834.87 ticks)
*  1731+ 1033                           67.0000       58.7491            12.31%
Found incumbent of value 67.000000 after 6.63 sec. (1824.17 ticks)
*  1731+  688                           65.0000       59.0933             9.09%
Found incumbent of value 65.000000 after 7.25 sec. (2079.31 ticks)
*  1731+  458                           62.0000       60.0000             3.23%
Found incumbent of value 62.000000 after 7.47 sec. (2162.68 ticks)
*  1731+  305                           61.0000       60.0000             1.64%
Found incumbent of value 61.000000 after 8.20 sec. (2495.45 ticks)
*  1731+    0                           60.0000       60.0000             0.00%
Found incumbent of value 60.000000 after 8.58 sec. (2603.40 ticks)
*  1731     0      integral     0       60.0000       60.0000    10141    0.00%
Found incumbent of value 60.000000 after 8.61 sec. (2604.50 ticks)

Cover cuts applied:  150
Implied bound cuts applied:  14
Flow cuts applied:  37
Mixed integer rounding cuts applied:  249
Gomory fractional cuts applied:  26

Root node processing (before b&c):
  Real time             =    1.31 sec. (273.18 ticks)
Parallel b&c, 4 threads:
  Real time             =    7.30 sec. (2331.56 ticks)
  Sync time (average)   =    0.25 sec.
  Wait time (average)   =    0.01 sec.
                          ------------
Total (root+branch&cut) =    8.61 sec. (2604.75 ticks)
MIP status(101): integer optimal solution


CBC Log



Calling CBC main solution routine...
Integer solution of 74 found by feasibility pump after 0 iterations and 0 nodes (2.78 seconds)
Integer solution of 72 found by RINS after 0 iterations and 0 nodes (2.96 seconds)
128 added rows had average density of 31.601563
At root node, 128 cuts changed objective from 55.26645 to 55.416026 in 10 passes
Cut generator 0 (Probing) - 367 row cuts average 2.1 elements, 0 column cuts (12 active)  in 0.022 seconds - new frequency is 1
Cut generator 1 (Gomory) - 598 row cuts average 26.1 elements, 0 column cuts (0 active)  in 0.090 seconds - new frequency is 1
Cut generator 2 (Knapsack) - 14 row cuts average 11.9 elements, 0 column cuts (0 active)  in 0.037 seconds - new frequency is -100
Cut generator 3 (Clique) - 0 row cuts average 0.0 elements, 0 column cuts (0 active)  in 0.003 seconds - new frequency is -100
Cut generator 4 (MixedIntegerRounding2) - 368 row cuts average 11.2 elements, 0 column cuts (0 active)  in 0.023 seconds - new frequency is 1
Cut generator 5 (FlowCover) - 394 row cuts average 2.8 elements, 0 column cuts (0 active)  in 0.041 seconds - new frequency is 1
Cut generator 6 (TwoMirCuts) - 598 row cuts average 35.5 elements, 0 column cuts (0 active)  in 0.072 seconds - new frequency is -100
After 0 nodes, 1 on tree, 72 best solution, best possible 55.416026 (3.94 seconds)
Integer solution of 70 found by heuristic after 4138 iterations and 57 nodes (14.24 seconds)
Integer solution of 69 found by heuristic after 12712 iterations and 287 nodes (23.32 seconds)
Integer solution of 66 found by heuristic after 18149 iterations and 487 nodes (25.94 seconds)
After 1005 nodes, 555 on tree, 66 best solution, best possible 55.416026 (31.73 seconds)
Integer solution of 65 found by heuristic after 32591 iterations and 1015 nodes (33.93 seconds)
Integer solution of 64 found by heuristic after 43252 iterations and 1405 nodes (39.79 seconds)
Integer solution of 63 found by heuristic after 52409 iterations and 1805 nodes (44.62 seconds)
After 2017 nodes, 1104 on tree, 63 best solution, best possible 55.416026 (45.77 seconds)
After 3045 nodes, 1653 on tree, 63 best solution, best possible 55.416026 (52.29 seconds)
After 4099 nodes, 2212 on tree, 63 best solution, best possible 55.416026 (55.02 seconds)
After 5163 nodes, 2769 on tree, 63 best solution, best possible 55.416026 (57.08 seconds)

. . .

After 131221 nodes, 37229 on tree, 63 best solution, best possible 55.416026 (610.94 seconds)
After 132282 nodes, 37230 on tree, 63 best solution, best possible 55.416026 (613.18 seconds)
After 133298 nodes, 37231 on tree, 63 best solution, best possible 55.416026 (615.50 seconds)
After 134320 nodes, 37318 on tree, 63 best solution, best possible 55.416026 (621.40 seconds)
Integer solution of 62 found by heuristic after 2839018 iterations and 134502 nodes (621.99 seconds)
After 135334 nodes, 37422 on tree, 62 best solution, best possible 55.416026 (627.07 seconds)
After 136352 nodes, 37407 on tree, 62 best solution, best possible 55.416026 (631.83 seconds)
After 137391 nodes, 37395 on tree, 62 best solution, best possible 55.416026 (637.74 seconds)
After 138400 nodes, 37385 on tree, 62 best solution, best possible 55.416026 (642.25 seconds)

 . . .

After 1566320 nodes, 37408 on tree, 62 best solution, best possible 55.416026 (7177.35 seconds)
After 1567325 nodes, 37412 on tree, 62 best solution, best possible 55.416026 (7182.33 seconds)
After 1568336 nodes, 37421 on tree, 62 best solution, best possible 55.416026 (7187.07 seconds)
After 1569358 nodes, 37402 on tree, 62 best solution, best possible 55.416026 (7192.93 seconds)
After 1570410 nodes, 37400 on tree, 62 best solution, best possible 55.416026 (7199.07 seconds)
Thread 0 used 30010 times,  waiting to start 2696,  0 locks, 0 locked, 0 waiting for locks
Thread 1 used 30010 times,  waiting to start 2480,  0 locks, 0 locked, 0 waiting for locks
Thread 2 used 30010 times,  waiting to start 2083,  0 locks, 0 locked, 0 waiting for locks
Thread 3 used 30010 times,  waiting to start 1770,  0 locks, 0 locked, 0 waiting for locks
Main thread 6737 waiting for threads,  0 locks, 0 locked, 0 waiting for locks
Exiting on maximum time
Partial search - best objective 62 (best possible 55.416026), took 19832056 iterations and 1570713 nodes (7202.49 seconds)
Strong branching done 3540964 times (6897 iterations), fathomed 137838 nodes and fixed 779663 variables
Maximum depth 198, 2057372 variables fixed on reduced cost

Time limit reached. Have feasible solution.
MIP solution:    6.200000e+01   (1570713 nodes, 7202.62 CPU seconds, 7202.62 wall clock seconds)

Friday, March 6, 2009

A conference scheduling problem (2)

In this posting I described the solution for a conference scheduling problem. Now the question is posed: can we add a constraint on the room capacity: up to 15 people per room. The first thing I did was to inspect my solution. Indeed we are exceeding this limit here and there:
schedule2 
In row total some of the occupancy counts are larger than 15. Note that this was a solution with objective=1491. We can add the room capacity constraint as follows:

roomcap 
Using this additional constraint, the solution looks like:
schedule3
This reduces the optimal objective from 1491 to 1487. I.e. we pay for this with a small decrease w.r.t. the preferences. The solution time was 2 minutes with GAMS/Cplex.

I use here the fact that all rooms are identical. If there are five rooms with different capacity, we need to know how talks are assigned to individual rooms. That requires extra binary variables (either by adding a room index to variable x or by introducing a new variable that handles the room assignment).

A conference scheduling problem

 

From: GagoX <elgrang...@gmail.com>
Date: Mar 3, 11:43 am
Subject: scheduling problem optimizing preferences
To: sci.math

Hi everyone,

this is a real life problem and I have no idea even how to start!

I need to organize a small conference:

Np=50 participants (P1 to P50) and Nt=13 talks (T1 to T13).
There are 5 time spots each with 5 rooms available.
T1 will be given 3 times, T2 to T7 will be given 2 times each and T8
to T13 will be given only once. Consequently there are 22 talks. The
constraint is that the repeated talks should not be scheduled in the
same time slot.

Each participant has given his preference to which talk to attend,
from 1st preference to 8th preference. And each participant should
attend 5 talks, one in each time slot.

Problem: What talks  should be scheduled in each time slot so to
optimize the preferences?

The optimum solution would be to fulfill that each participand attend
their 5 first preferences.

How is this problem called and is it possible to solve...what should
be the strategy.Or even better, does someone know the solution?

I guess if I knew how to ennumerate  each possibility (I do not know),
I could then quantify the fulfilling of the preferences and then take
the best one (brute force) (of course programming the whole
thing)...but I am afraid that there are too many possibilities!

Thaks a lot in advance!!!!

This is a task that is sometimes very well suited to be implemented as mixed integer programming problem. (If they become too big, scheduling problems can be better implemented using different techniques.)

Lets try to do this quickly in GAMS. We start with the sets, and the basic data:

set
p 'participants' /p1*p50/
t 'presenter' /t1*t13/
n 'talk number' /n1*n3/
s 'timeslot' /slot1*slot5/

;

scalar rooms 'number of parallel sessions' /5/

set talk(t,n) 'each presenter can give several talks' /
t1.(n1,n2,n3)
(t2*t7).(n1,n2)
(t8*t13).n1
/;

scalar numtalk 'total number of talks';
numtalk=card(talk);
display talk,numtalk;


** actually the count is 21
** abort$(numtalk<>22) "oops, check your sets";

parameter ntalk(t) 'numbers of times a talk is given';
ntalk(t) = sum(talk(t,n),1);
display ntalk;


We see that the total number of talks is actually 21.



The preferences can be modeled as a parameter preferences(p,t). We assume eight of each row has numbers 1,..,8 and the rest is zero (no preference). We assume further 8 is highest preference so we will maximize. To be able to run a model we need to simulate some data. We can use random data, but need to consider that talks t1 and t2 through t7 are a little bit more popular (they are repeated a few times). The algorithm is a little bit complicated, but here it is:



parameter italk(t,n) 'number all talks (all 21 of them)';
scalar counter/0/;
loop(talk(t,n),
counter=counter+1;
italk(talk)=counter;
);
display italk;

parameter preferences(p,t) 'preference = 0..8, 8 is highest preference';
preferences(p,t)=0;

scalar kk,kt;
alias(t,tt);
set tcurrent(t);
loop((p,tt)$(ord(tt)<=8),

repeat
* draw from 1..numtalk
kk = UniformInt(1,numtalk);
kt = sum(talk(t,n)$(italk(t,n)=kk),ord(t));
* preferences(p,'element with ord kt') = ord(t)
tcurrent(t)$(ord(t)=kt) = yes;
if (sum(tcurrent,preferences(p,tcurrent))=0,
preferences(p,tcurrent) = ord(tt);
else
kk = 0
);
tcurrent(tcurrent) = no;
until kk<>0;

);

display "after",preferences


We renumber talks in italks as follows:



----     84 PARAMETER italk  number all talks (all 21 of them)

n1 n2 n3

t1 1.000 2.000 3.000
t2 4.000 5.000
t3 6.000 7.000
t4 8.000 9.000
t5 10.000 11.000
t6 12.000 13.000
t7 14.000 15.000
t8 16.000
t9 17.000
t10 18.000
t11 19.000
t12 20.000
t13 21.000


This allows us to draw from unique talks 1..21, which gives a better distribution than if we would have drawn from 1..13 (e.g. we would generate too few attendants for the popular talk t1 which is given three times). Using this we can generate some data for preferences:



----    110 PARAMETER preferences  preference = 0..8, 8 is highest preference

t1 t2 t3 t4 t5 t6 t7 t8 t9

p1 6.000 1.000 4.000 5.000 7.000 3.000
p2 4.000 6.000 7.000 8.000 1.000 5.000 3.000
p3 2.000 3.000 8.000 1.000 4.000 6.000 7.000
p4 1.000 3.000 5.000 2.000 6.000 8.000 7.000
p5 3.000 5.000 4.000 2.000 1.000 7.000 6.000 8.000
p6 4.000 7.000 1.000 8.000 5.000 2.000 3.000 6.000
p7 3.000 7.000 2.000 1.000 8.000 6.000 5.000
p8 7.000 1.000 2.000 4.000 8.000 5.000
p9 1.000 6.000 7.000 3.000 4.000 2.000 5.000
p10 2.000 5.000 3.000 1.000 7.000 6.000 8.000
p11 7.000 6.000 3.000 5.000 2.000 4.000
p12 7.000 1.000 5.000 8.000 2.000 6.000 3.000
p13 8.000 1.000 4.000 6.000 2.000 3.000
p14 2.000 1.000 5.000 3.000 4.000 6.000
p15 2.000 3.000 6.000 5.000 8.000 1.000 7.000
p16 5.000 7.000 1.000 3.000 8.000 2.000
p17 4.000 1.000 8.000 6.000 5.000
p18 3.000 1.000 2.000 5.000 7.000 6.000 4.000
p19 6.000 8.000 7.000 5.000 1.000 4.000
p20 5.000 1.000 6.000 8.000 4.000
p21 1.000 2.000 5.000 3.000 7.000
p22 4.000 1.000 8.000 5.000 3.000 6.000 7.000
p23 2.000 5.000 6.000 8.000 3.000
p24 1.000 4.000 5.000 7.000 6.000 2.000 3.000 8.000
p25 2.000 4.000 6.000 5.000 1.000 7.000
p26 3.000 5.000 7.000 8.000 4.000 6.000
p27 2.000 6.000 8.000 1.000 4.000 3.000 7.000
p28 4.000 1.000 3.000 6.000 7.000 8.000
p29 2.000 3.000 4.000 8.000 1.000 5.000 6.000
p30 4.000 1.000 3.000 8.000 2.000 6.000 5.000
p31 5.000 6.000 2.000 7.000 1.000 4.000
p32 6.000 3.000 4.000 5.000 7.000 8.000
p33 2.000 4.000 6.000 5.000 1.000 8.000
p34 7.000 4.000 3.000 6.000 5.000
p35 1.000 7.000 8.000 2.000 6.000 4.000 3.000
p36 2.000 5.000 3.000 6.000 1.000 7.000
p37 1.000 3.000 5.000 4.000 6.000 2.000
p38 7.000 3.000 8.000 6.000 2.000 1.000
p39 2.000 1.000 4.000 8.000 7.000 5.000
p40 5.000 1.000 4.000 8.000 7.000 2.000 3.000
p41 4.000 7.000 2.000 3.000 5.000 6.000
p42 2.000 8.000 7.000 5.000 4.000 6.000
p43 5.000 2.000 7.000 6.000 1.000 3.000
p44 4.000 7.000 1.000 3.000 5.000
p45 3.000 7.000 1.000 4.000 5.000 8.000 2.000
p46 2.000 5.000 6.000 8.000 4.000 7.000
p47 7.000 5.000 3.000 8.000 2.000 1.000
p48 5.000 7.000 8.000 6.000 3.000
p49 2.000 5.000 1.000 3.000 8.000
p50 2.000 5.000 1.000 3.000 4.000 7.000

+ t10 t11 t12 t13

p1 2.000 8.000
p2 2.000
p3 5.000
p4 4.000
p7 4.000
p8 6.000 3.000
p9 8.000
p10 4.000
p11 1.000 8.000
p12 4.000
p13 5.000 7.000
p14 8.000 7.000
p15 4.000
p16 4.000 6.000
p17 7.000 3.000 2.000
p18 8.000
p19 3.000 2.000
p20 2.000 7.000 3.000
p21 4.000 6.000 8.000
p22 2.000
p23 7.000 1.000 4.000
p25 3.000 8.000
p26 2.000 1.000
p27 5.000
p28 5.000 2.000
p29 7.000
p30 7.000
p31 3.000 8.000
p32 2.000 1.000
p33 3.000 7.000
p34 8.000 2.000 1.000
p35 5.000
p36 8.000 4.000
p37 8.000 7.000
p38 4.000 5.000
p39 3.000 6.000
p40 6.000
p41 8.000 1.000
p42 1.000 3.000
p43 8.000 4.000
p44 6.000 8.000 2.000
p45 6.000
p46 1.000 3.000
p47 6.000 4.000
p48 2.000 1.000 4.000
p49 6.000 4.000 7.000
p50 6.000 8.000


Of course in practice we have his data available and we don't have to worry about this step (actually the most complicated part of the whole model). The rest of the model was implemented as follows:



variable z 'objective variable';
binary variables
x(t,p,s) 'assign talk/person/slot'
xts(t,s) 'assign talk/slot'
xtp(t,p) 'assign talk/person'
;

* we can relax xts and xtp
xts.prior(t,s) = INF;
xtp.prior(t,p) = INF;


equations
defxts1(t,s) 'calculate xts: all x=0 => xts = 0'
defxts2(t,p,s) 'calculate xts: any x=1 => xts = 1'

defxtp(t,p) 'calculate xtp'

talkcount(t) 'talk can be repeated ntalk times'
slotcount(s) 'up to 5 talks each period'

listen(p,s) 'p can visit only one talk in each time period'
zdef 'objective: maximize preferences'
;

* x(t,p,s)=0 for all p => xts(t,s) = 0
defxts1(t,s).. xts(t,s) =L= sum(p, x(t,p,s));
* any x(t,p,s)=1 => xts(t,s) = 1
defxts2(t,p,s).. xts(t,s) =G= x(t,p,s);

* p visits talk t in any s
defxtp(t,p).. xtp(t,p) =E= sum(s, x(t,p,s));

* each talk happens exactly ntalk times
talkcount(t).. sum(s, xts(t,s)) =E= ntalk(t);

* timeslot can only hold up to 5 talks
slotcount(s).. sum(t, xts(t,s)) =L= rooms;

* p can only visit one talk in each time period
listen(p,s).. sum(t,x(t,p,s)) =E= 1;

* we don't allow here (t,p) combinations without preference
xtp.fx(t,p)$(preferences(p,t)=0) = 0;

* objective: maximize
zdef.. z =e= sum((t,p), preferences(p,t) * xtp(t,p));


model scheduling /all/;


option mip=cplex;
scheduling.optfile=1;
scheduling.iterlim=100000;
scheduling.optcr=0;
solve scheduling using mip maximizing z;


$onecho > cplex.opt
threads 4
$offecho


Note that variables xts and xtp are automatically integer, so we relax them by assigning a priority of infinity to them.



Cplex solves this quite quickly:



--- Job conference2.gms Start 03/05/09 17:58:00 WEX-VIS 23.0.2 x86/MS Windows       
GAMS Rev 230 Copyright (C) 1987-2009 GAMS Development. All rights reserved
Licensee: Erwin Kalvelagen G090213/0001CV-WIN
Amsterdam Optimization Modeling Group DC4572
--- Starting compilation
--- conference2.gms(177) 3 Mb
--- Starting execution: elapsed 0:00:00.003
--- conference2.gms(169) 4 Mb
--- Generating MIP model scheduling
--- conference2.gms(170) 5 Mb
--- 4,234 rows 3,966 columns 17,496 non-zeroes
--- 3,250 discrete-columns
*** 465 relaxed-columns WARNING
--- Executing CPLEX: elapsed 0:00:00.034

ILOG CPLEX Feb 14, 2009 23.0.2 WIN 9101.9411 VIS x86/MS Windows
Cplex 11.2.1, GAMS Link 34
Cplex licensed for 1 use of lp, qp, mip and barrier, with 4 parallel threads.

Reading parameter(s) from "C:\projects\test\cplex.opt"
>> threads 4
Finished reading from "C:\projects\test\cplex.opt"
Reading data...
Starting Cplex...
Tried aggregator 1 time.
MIP Presolve eliminated 1501 rows and 1501 columns.
Reduced MIP has 2733 rows, 2465 columns, and 10595 nonzeros.
Reduced MIP has 2000 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.00 sec.
Clique table members: 650.
MIP emphasis: balance optimality and feasibility.
MIP search method: dynamic search.
Parallel mode: opportunistic, using up to 4 threads.
Parallel mode: opportunistic, using up to 4 threads for concurrent optimization.
Tried aggregator 1 time.
No LP presolve or aggregator reductions.
Using devex.
Using devex.

Total real time on 4 threads = 0.17 sec.
Root relaxation solution time = 0.17 sec.

Nodes Cuts/
Node Left Objective IInf Best Integer Best Node ItCnt Gap

0 0 1500.0000 906 1500.0000 5
* 0+ 0 1272.0000 1500.0000 5 17.92%
0 0 1500.0000 779 1272.0000 Fract: 1 3652 17.92%
* 0+ 0 1308.0000 1500.0000 3652 14.68%
* 0+ 0 1353.0000 1500.0000 3652 10.86%
* 0+ 0 1446.0000 1500.0000 3652 3.73%
0 2 1500.0000 779 1446.0000 1500.0000 3652 3.73%
* 4+ 0 1460.0000 1500.0000 10828 2.74%
* 4+ 0 1471.0000 1500.0000 10683 1.97%
* 40+ 33 1472.0000 1498.0000 37861 1.77%
100 95 1492.8125 568 1472.0000 1498.0000 54702 1.77%
* 127+ 120 1478.0000 1498.0000 58492 1.35%
200 194 1487.6000 458 1478.0000 1498.0000 74738 1.35%
300 291 1492.6364 499 1478.0000 1498.0000 88945 1.35%
* 346+ 323 1483.0000 1498.0000 101352 1.01%
* 374+ 323 1488.0000 1498.0000 108821 0.67%
400 253 1493.0667 555 1488.0000 1498.0000 115116 0.67%
500 153 1495.0000 654 1488.0000 1498.0000 148604 0.67%
600 159 1491.4444 448 1488.0000 1497.3333 208207 0.63%
700 205 1492.8333 526 1488.0000 1496.6667 247331 0.58%
800 243 1494.6667 438 1488.0000 1496.6667 263583 0.58%
900 312 cutoff 1488.0000 1496.5000 282888 0.57%
1000 385 1494.9375 465 1488.0000 1496.0000 309440 0.54%
Elapsed real time = 32.45 sec. (tree size = 0.49 MB, solutions = 10)
1100 457 1492.1875 579 1488.0000 1495.7500 326655 0.52%
1200 524 cutoff 1488.0000 1495.5000 347873 0.50%
1300 588 1490.5000 386 1488.0000 1495.3333 371387 0.49%
1400 655 1489.4286 429 1488.0000 1495.0000 394081 0.47%
1500 706 cutoff 1488.0000 1495.0000 418373 0.47%
1600 760 cutoff 1488.0000 1494.9167 445114 0.46%
1700 810 1489.5000 355 1488.0000 1494.7500 466940 0.45%
1800 865 cutoff 1488.0000 1494.6667 487877 0.45%
1900 924 1490.3333 385 1488.0000 1494.5000 510279 0.44%
2000 972 1492.5000 523 1488.0000 1494.3333 536279 0.43%
Elapsed real time = 43.77 sec. (tree size = 1.27 MB, solutions = 10)
2100 1022 cutoff 1488.0000 1494.1429 561289 0.41%
* 2127 391 integral 0 1491.0000 1494.0714 567476 0.21%
2200 380 cutoff 1491.0000 1494.0000 590101 0.20%
2300 363 1492.0000 530 1491.0000 1493.6667 627287 0.18%
2400 358 cutoff 1491.0000 1493.5000 652433 0.17%
2500 326 cutoff 1491.0000 1493.2000 684303 0.15%
2600 272 1492.5625 605 1491.0000 1493.0000 722077 0.13%
2700 245 cutoff 1491.0000 1493.0000 749425 0.13%
2800 191 1492.0000 334 1491.0000 1492.5000 771850 0.10%
2900 107 cutoff 1491.0000 1492.2609 793601 0.08%
3000 15 cutoff 1491.0000 1492.0000 808231 0.07%
Elapsed real time = 57.28 sec. (tree size = 0.05 MB, solutions = 11)

Root node processing (before b&c):
Real time = 2.64
Parallel b&c, 4 threads:
Real time = 54.99
Sync time (average) = 2.47
Wait time (average) = 0.00
-------
Total (root+branch&cut) = 57.63 sec.
MIP status(101): integer optimal solution
Fixing integer variables, and solving final LP...
Parallel mode: opportunistic, using up to 4 threads for concurrent optimization.
Tried aggregator 1 time.
LP Presolve eliminated 4234 rows and 3966 columns.
All rows and columns eliminated.

Total real time on 4 threads = 0.00 sec.
Fixed MIP status(1): optimal

Proven optimal solution.

MIP Solution: 1491.000000 (814080 iterations, 3023 nodes)
Final Solve: 1491.000000 (0 iterations)

Best possible: 1491.000000
Absolute gap: 0.000000
Relative gap: 0.000000

--- Restarting execution
--- conference2.gms(170) 0 Mb
--- Reading solution for model scheduling
--- conference2.gms(170) 3 Mb
--- GDX File C:\projects\test\x.gdx
*** Status: Normal completion
--- Job conference2.gms Stop 03/05/09 17:58:58 elapsed 0:00:57.817

Note that we found a proven global optimum in less than a minute here. The complete schedule looks like:




schedule 
It is often the simplest to start with a single large multidimensional “cube” (our variable x(t,p,s)), and then derive auxiliary variables from that cube (our variables xts, xtp). If the problem becomes very large, this may not be possible (x just becomes too large). However, if this structure fits, in many cases the performance is very good. In this case we have 3250 binary variables. This is a large number. Is is quite a feat that we can solve this quickly to optimality.



See also [follow-up].

Thursday, February 12, 2009

TSP Powerset Formulation

> I'm a PhD student in Portugal and I´m modeling a Vehicle Routing
> Problem. I have some difficulties to modelling this subtour
> elimination constraint (n = number of nodes):

> sum(i in S, sum(j in S, x(i,j))) <= |S|-1
> for every nonempty subset S of {2,3,..,n}


This is the Ford, Fulkerson, Johnson (1954) formulation, based on the power of {2,3,..,n}. This generates a lot of constraints (2^(n-1)), with many not active in the optimal solution. So this approach only works for small problems.

$ontext

  
Burma 14 city problem using power set formulation

  
Erwin Kalvelagen, Amsterdam Optimization

  
References:
       
Gerhard Reinelt, Universitaet Heidelberg, TSPLIB95
       
A.J. Orman & H.P. Williams, A Survey of Different Integer Programming
           
Formulations of the Travelling Salesman Problem

$offtext


$eolcom //

sets
   i
/city1*city14/
   xy
/x,y/
;
alias(i,j);

table coordinates(i,xy) 'coordinates from tsplib'

          
x            y
  
city1  16.47       96.10
  
city2  16.47       94.44
  
city3  20.09       92.54
  
city4  22.39       93.37
  
city5  25.23       97.24
  
city6  22.00       96.05
  
city7  20.47       97.02
  
city8  17.20       96.29
  
city9  16.30       97.38
 
city10  14.05       98.12
 
city11  16.53       97.38
 
city12  21.52       95.59
 
city13  19.41       97.13
 
city14  20.09       94.55
;

*
* form the distance matrix
*
parameter latitude(i), longitude(i), degree(i,xy), minute(i,xy);
degree(i,xy) = trunc(coordinates(i,xy));
minute(i,xy) = coordinates(i,xy) - trunc(coordinates(i,xy));
latitude(i) = pi*(degree(i,
'x')+5.0*minute(i,'x'
)/3.0)/180.0;
longitude(i) = pi*(degree(i,
'y')+5.0*minute(i,'y'
)/3.0)/180.0;


set
nd(i,j);
nd(i,j)$(
not sameas(i,j)) = yes
;


scalar rrr /6378.388/
;
parameter
q1(i,j),q2(i,j),q3(i,j);
q1(nd(i,j)) = cos(longitude(i) - longitude(j));
q2(nd(i,j)) = cos(latitude(i) - latitude(j));
q3(nd(i,j)) = cos(latitude(i) + latitude(j));

parameter c(i,j) 'distance matrix (KM)'
;
c(nd(i,j)) = trunc(RRR * arccos( 0.5*((1.0+q1(i,j))*q2(i,j) - (1.0-q1(i,j))*q3(i,j)) ) + 1.0);
display
c;


*

* form the power set
*
set v(i) 'exclude city 1' /city2*city14/;
abort$(card(i)<>card(v)+1) 'Set v is incorrect'
,i,v;
set n 'subset id (max number of subsets)' /n1*n8192/
;

scalar nsize 'size needed for set n'
;
nsize = 2**
card
(v);
abort$(card(n)<nsize) 'set n is too small'
,nsize;

sets

  base
'used in next set' /no,yes/
  ps0(n,v,base)
/ system.powersetRight/
  ps(n,v)
'power set'
;
ps(n,v) = ps0(n,v,
'yes');


parameter
pscount(n);
pscount(n) =
sum
(ps(n,v),1);

*

* form subsets, exclude subsets with cardinality = 1
*
set nsub(n);
nsub(n)$(pscount(n)>=2) =
yes
;

*

* form ps2(n,i,j) = ps(n,i) and ps(n,j)
* this will simplify the subtour elimination constraint
*
alias(v,vv);
set
ps2(n,i,j);
ps2(nsub(n),nd(v,vv))$(ps(n,v)
and ps(n,vv)) = yes
;

*

* here is the model
*
binary variables x(i,j);
variable z 'objective variable'
;

equations

   obj 
'objective'
   assign1(i)
'assignment problem constraint'
   assign2(j)
'assignment problem constraint'
   subt(n)   
'subtour elimination'
;

obj..   z =e=
sum(nd(i,j), c(i,j)*x(i,j));
assign1(i)..
sum
(nd(i,j), x(i,j)) =e= 1;
assign2(j)..
sum
(nd(i,j), x(i,j)) =e= 1;
subt(nsub(n))..
sum
(ps2(n,i,j),x(i,j)) =L=  pscount(n)-1;

option
optcr=0;
model tsp /all/
;
solve
tsp minimizing z using mip;

Note: the construct system.powerSetRight is a new GAMS feature (24.0, 2013).

This solves quite fast:

--- Starting compilation
--- burma14.gms(122) 9 Mb
--- Starting execution: elapsed 0:00:00.028
--- burma14.gms(120) 21 Mb
--- Generating MIP model tsp
--- burma14.gms(122) 44 Mb
---   8,207 rows  183 columns  320,035 non-zeroes
---   182 discrete-columns
--- Executing CPLEX: elapsed 0:00:00.741

IBM ILOG CPLEX   24.7.3 r58181 Released Jul 11, 2016 WEI x86 64bit/MS Windows
--- GAMS/Cplex licensed for continuous and discrete problems.
Cplex 12.6.3.0

Reading data...
Starting Cplex...
Space for names approximately 0.16 Mb
Use option 'names no' to turn use of names off
Tried aggregator 1 time.
MIP Presolve eliminated 1 rows and 1 columns.
Reduced MIP has 8206 rows, 182 columns, and 319852 nonzeros.
Reduced MIP has 182 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.28 sec. (95.59 ticks)
Probing time = 0.03 sec. (15.13 ticks)
Tried aggregator 1 time.
Reduced MIP has 8206 rows, 182 columns, and 319852 nonzeros.
Reduced MIP has 182 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.28 sec. (95.59 ticks)
Probing time = 0.03 sec. (15.13 ticks)
Clique table members: 106.
MIP emphasis: balance optimality and feasibility.
MIP search method: dynamic search.
Parallel mode: none, using 1 thread.
Tried aggregator 1 time.
DUAL formed by presolve
Reduced LP has 182 rows, 8388 columns, and 320034 nonzeros.
Presolve time = 0.08 sec. (27.42 ticks)

Iteration log . . .
Iteration:     1    Objective     =            70.000000
Initializing dual steep norms . . .
Root relaxation solution time = 0.16 sec. (57.42 ticks)

        Nodes                                         Cuts/
   Node  Left     Objective  IInf  Best Integer    Best Bound    ItCnt     Gap

*     0     0      integral     0     3323.0000     3323.0000       45    0.00%
Elapsed time = 1.30 sec. (460.29 ticks, tree = 0.00 MB, solutions = 1)
Found incumbent of value 3323.000000 after 1.30 sec. (460.29 ticks)

Root node processing (before b&c):
  Real time             =    1.30 sec. (460.33 ticks)
Sequential b&c:
  Real time             =    0.00 sec. (0.00 ticks)
                          ------------
Total (root+branch&cut) =    1.30 sec. (460.33 ticks)
MIP status(101): integer optimal solution
Cplex Time: 1.30sec (det. 460.33 ticks)
Fixing integer variables, and solving final LP...
Tried aggregator 1 time.
LP Presolve eliminated 8207 rows and 183 columns.
All rows and columns eliminated.
Presolve time = 0.03 sec. (13.14 ticks)
Fixed MIP status(1): optimal
Cplex Time: 0.03sec (det. 17.45 ticks)

Proven optimal solution.

MIP Solution:         3323.000000    (45 iterations, 0 nodes)
Final Solve:          3323.000000    (0 iterations)

Best possible:        3323.000000
Absolute gap:            0.000000
Relative gap:            0.000000

--- Restarting execution
--- burma14.gms(122) 20 Mb
--- Reading solution for model tsp
--- burma14.gms(122) 20 Mb
*** Status: Normal completion
--- Job burma14.gms Stop 02/23/17 00:47:38 elapsed 0:00:02.719

image

References
  1. burma14.gms: above model
  2. burma14-3.gms: generation of powerset written in GAMS (not using system.PowerSetRight).
  3. burma14-2.gms: formulation from Svestka (J.A. Svestka, A continuous variable representation of the TSP, Math Prog, v15, 1978, pp211-213)
  4. burma14-4.gms: a cutting plane technique

Easy MIP

In this post we showed a very difficult mip model with just 217 0-1 variables. Here is a very large MIP model that shows the opposite behavior. Although it has about 230k integer variables, Cplex devours it:


---   122,284 rows  352,038 columns  667,797 non-zeroes
--- 231,136 discrete-columns

Nodes Cuts/
Node Left Objective IInf Best Integer Best Node ItCnt Gap

0 0 588575.0000 606 588575.0000 14792
0 0 588575.0000 689 Cuts: 313 16547
0 0 588575.0000 736 ZeroHalf: 14 17624
* 0+ 0 587775.0000 588575.0000 17624 0.14%
0 2 588575.0000 349 587775.0000 588575.0000 17624 0.14%
Elapsed real time = 30.14 sec. (tree size = 0.00 MB, solutions = 1)
* 10+ 1 588575.0000 588575.0000 18686 0.00%

Total turnaround time (including GAMS): 46 seconds. A good illustration that size of the problem is not a good indicator for difficulty. (Don't know much about the model as it was sent to me in LP format. There may be many variables automatically integer-valued).

Thursday, January 29, 2009

Gurobi vs Cplex benchmarks

> What are your first impressions of Gurobi? How does it compare to CPLEX for MIP? Have you done any benchmark analysis?

Here are some benchmarks: http://plato.asu.edu/ftp/milpc.html

However I would always urge you to try out solvers on your particular models as they may behave very differently than the benchmark models. Drop me a note if you need me to run some models or need access to evaluation systems.

Wednesday, January 28, 2009

Cplex log: number of integer variables

Sometimes progress logs pose some interesting questions. In the Cplex log below we solve a problem with 2016 binary variables (after presolving). However the progress log seems to indicate that when we start 2036 of them are integer infeasible.

Reading data...
Starting Cplex...
Tried aggregator 1 time.
MIP Presolve eliminated 45077 rows and 15073 columns.
MIP Presolve modified 504 coefficients.
Aggregator did 1008 substitutions.
Reduced MIP has 73884 rows, 26656 columns, and 201936 nonzeros.
Reduced MIP has 2016 binaries, 0 generals, 0 SOSs, and 0 indicators.
Presolve time = 0.45 sec.
Clique table members: 900.
MIP emphasis: hidden feasible solutions.
MIP search method: dynamic search.
Parallel mode: opportunistic, using up to 4 threads.
Parallel mode: opportunistic, using up to 4 threads for concurrent optimization.
Using devex.
Using devex.

Total real time on 4 threads = 16.18 sec.
Root relaxation solution time = 16.19 sec.

Nodes Cuts/
Node Left Objective IInf Best Integer Best Node ItCnt Gap

0 0 0.0000 2036 0.0000 20

Wednesday, January 21, 2009

Cplex barrier results

With some simulated data for the problem described in this post, we achieved some very good results with the Cplex barrier method. Below are timings in seconds with different Cplex algorithms


rows/cols/nzdualprimalbarrier
model 11e5/2e5/1.4e612478578.7
model 21.1e5/2.1e5/6.1e519512237.3



The GAMS models look like:
41  variable z,a1(j),a2(j),s1(i),s2(i),y(k);
42 positive variable s1,s2;
43 equation obj,e1(i),e2(k),e3(i);
44
45 option lp=cplex;
46 option iterlim=1000000;
47 option reslim=10000;
48
49 obj.. z =e= sum(i, s1(i)+s2(i));
50 e1(i).. sum(j, xx(i,j)*a1(j)) + s1(i) - s2(i) =e= b(i);
51 model m1 /obj,e1/;
52 solve m1 minimizing z using lp;
53
54 e2(k).. y(k) =e= sum(j, x(k,j)*a2(j));
55 e3(i).. sum(map(i,k), y(k)) + s1(i) - s2(i) =e= b(i);
56 model m2 /obj,e2,e3/;
57 *solve m2 minimizing z using lp;


Note that the SUM in line 55 is actually not a real summation. It just selects a k belonging to a particular i. A different, maybe better, way to write this would be:

equation e3(i,k);
e3(map(i,k)).. y(k) + s1(i) - s2(i) =e= b(i);

Friday, January 9, 2009

Sensitivity Analysis in a loop with GAMS/Cplex

> I have read the document http://www.gams.com/docs/sensitiv.htm but I don't
> see how I can do sensitivity analysis in a loop.

GAMS/Cplex writes sensitivity information to a text file (include file) and GAMS cannot read such a file at compile time. I.e. you cannot read a text file or include file to be specific inside a loop.

It would have been preferable in GAMS/Cplex would have been updated so that it can write sensitivity information to a GDX file (see also GAMS/Cplex wish list).

As a work around one can call a GAMS submodel from the GAMS main model. The submodel can then convert the include file to a GDX file, which then can be read by the main model. 

A complete example is below:

$ontext

shows how to do sensitivity analysis inside a single
GAMS job by using GDX files.


Erwin Kalvelagen, december 2003, revised jan 2009

$offtext

Sets
i canning plants / seattle, san-diego /
j markets / new-york, chicago, topeka / ;

Parameters

a(i) capacity of plant i in cases
/ seattle 350
san-diego 600 /

b(j) demand at market j in cases
/ new-york 325
chicago 300
topeka 275 / ;

Table d(i,j) distance in thousands of miles
new-york chicago topeka
seattle 2.5 1.7 1.8
san-diego 2.5 1.8 1.4 ;

Scalar f freight in dollars per case per thousand miles /90/ ;

Parameter c(i,j) transport cost in thousands of dollars per case ;

c(i,j) = f * d(i,j) / 1000 ;

Variables
x(i,j) shipment quantities in cases
z total transportation costs in thousands of dollars ;

Positive Variable x ;

Equations
cost define objective function
supply(i) observe supply limit at plant i
demand(j) satisfy demand at market j ;

cost .. z =e= sum((i,j), c(i,j)*x(i,j)) ;

supply(i) .. sum(j, x(i,j)) =l= a(i) ;

demand(j) .. sum(i, x(i,j)) =g= b(j) ;

Model m /all/ ;


*
* set options to cplex writes an include file with sensitivity
* information
*
$onecho > cplex.opt
objrng all
rhsrng all
rngrestart rng.inc
$offecho

m.optfile=1;
m.dictfile=2;

option lp=cplex;
Set rnglim /lo,up/;

*
* three different scenarios
*
set iter /iter1*iter3/;
parameter delta(iter);
delta(iter)$(ord(iter)>1) = 100;
display delta;


*
* write gams file that reads include file rng.inc and
* writes a GDX file (specified on the command line)
*
$onecho > inc2gdx.gms
set i,j,rnglim
$gdxin sets.gdx
$load i j rnglim
$include rng.inc
$offecho


*
* save the sets i,j,rnlim to gdx file sets.gdx
*
execute_unload 'sets.gdx',i,j,rnglim;


*
* parameters to hold ranges for equation DEMAND
*
parameter demandrange(j,rnglim);
parameter alldemandrange(iter,j,rnglim);


loop(iter,
a(i) = a(i) + delta(iter);

SOLVE m USING LP minimizing z;

*
* store the sensitivity information in a GDX file
*
execute '=gams.exe inc2gdx.gms lo=3 gdx=dump.gdx';

*
* get data from GDX file
*
execute_load 'dump.gdx',demandrange=demandRNG;

alldemandrange(iter,j,rnglim) = demandrange(j,rnglim);
);

display alldemandrange;